Constructed
FCC Tower #1016395 – Green Township, USA
Tower Location
Share this page
Registration Number
1016395
File Number
A1350741
Constructed Date
August 1, 1980
Structure Type
LTOWER
FAA Notification
FAA Study
2025-AGL-6455-OE
FAA Issue Date
June 2, 2025
Heights
Height of Structure
61.6 m / 202.1 ft
Ground Elevation
252.1 m / 827.1 ft
Overall Height Above Ground
64.3 m / 211.0 ft
Overall Height AMSL
316.4 m / 1,038.1 ft
Owners
Phone
Email
Contacts
Contact
Company
Everest Special LLC
Phone
Email
Related Applications
| Date | Purpose |
|---|---|
| February 11, 2026 | Amendment (AM) |
| April 8, 2024 | Original Construction (OC) |
| December 19, 2023 | Original Construction (OC) |
| September 18, 2018 | Administrative Update (AU) |
| December 30, 2016 | Administrative Update (AU) |
| October 11, 2016 | Administrative Update (AU) |
| June 20, 2016 | Administrative Update (AU) |
| November 1, 2013 | Administrative Update (AU) |
| November 7, 2012 | Original Construction (OC) |
| February 23, 2010 | Administrative Update (AU) |
| August 7, 2003 | Original Construction (OC) |
| June 28, 1999 | New (NE) |
Tower History
| Date | Description |
|---|---|
| February 11, 2026 | Supercede - Internal Correction Applied |
| February 11, 2026 | Supercede - Internal Correction Applied |
| February 11, 2026 | Amendment Received |
| February 11, 2026 | Application Granted |
| February 11, 2026 | Supercede - Internal Correction Applied |
| February 11, 2026 | Amendment Received |
| February 11, 2026 | Supercede - Internal Correction Applied |
| February 11, 2026 | Amendment Received |
| February 11, 2026 | Application Granted |
| February 11, 2026 | Supercede - Internal Correction Applied |
| February 11, 2026 | Supercede - Internal Correction Applied |
| February 11, 2026 | Application Granted |
| December 15, 2025 | Modification Received |
| December 15, 2025 | Modification Received |
| December 15, 2025 | Modification Received |
| April 8, 2024 | Application Granted |
| April 8, 2024 | Change of Ownership Received |
| December 19, 2023 | Change of Ownership Received |
| December 19, 2023 | Application Granted |
| September 18, 2018 | Administrative Update Received |
| September 18, 2018 | Application Granted |
| December 30, 2016 | Application Granted |
| December 30, 2016 | Administrative Update Received |
| October 11, 2016 | Administrative Update Received |
| October 11, 2016 | Application Granted |
| June 20, 2016 | Application Granted |
| June 20, 2016 | Administrative Update Received |
| November 1, 2013 | Administrative Update Received |
| November 1, 2013 | Application Granted |
| November 7, 2012 | Change of Ownership Received |
| November 7, 2012 | Application Granted |
| February 23, 2010 | Administrative Update Received |
| February 23, 2010 | Application Granted |
| August 7, 2003 | Change of Ownership Received |
| August 7, 2003 | Application Granted |