Constructed
map

Tower Location

Share this page
badge Registration Number
1303812
description File Number
A1248665
calendar_today Constructed Date
December 29, 2017
my_location Coordinates
42.2254, -89.0860
category Structure Type
MTOWER
flight

FAA Notification

FAA Study
2022-AGL-15633-OE
FAA Issue Date
March 8, 2023
height

Heights

Height of Structure
32.3 m / 106.0 ft
Ground Elevation
215.5 m / 707.0 ft
Overall Height Above Ground
33.8 m / 110.9 ft
Overall Height AMSL
249.3 m / 817.9 ft
business

Owners

business Company
SBA Towers X, LLC
badge FRN
person

Contacts

business Company
SBA Towers X, LLC
comment

Comments

event Date notes Comment
October 19, 2017 300-foot (~100-meter) buffer around the nest until the nestlings have fledged. EAS recommends that construction activity avoid the bird-nesting season (February 1-August 31). If construction activity occurs during the nesting season, a preconstruction
October 19, 2017 have fledged the nest.
October 19, 2017 If suitable nesting habitat must be removed during the nesting season, a qualified biologist should conduct a nesting bird survey to identify any potential nesting activity. If active nests are observed, construction activity must be prohibited within a
October 19, 2017 NEPA resolved per FONSI letter dated 10/18/2017, file number A1087279.
October 19, 2017 nesting survey will be required to determine if nesting activity occurs on site. If during the survey no nesting activity is observed, no further action is required. If nesting activity is observed, construction activity can proceed after the nestlings
apps

Related Applications

event Date unfold_more Purpose
July 17, 2023 Notification (NT)
July 17, 2023 Modification (MD)
June 26, 2018 Notification (NT)
June 26, 2018 Modification (MD)
April 18, 2018 Original Construction (OC)
January 2, 2018 Notification (NT)
October 19, 2017 Amendment (AM)
history

Tower History

event Date unfold_more description Description
July 17, 2023 Construction Notification Received
July 17, 2023 Application Granted
July 17, 2023 Construction Notification Received
July 17, 2023 Modification Received
July 17, 2023 Application Granted
June 26, 2018 Application Granted
June 26, 2018 Construction Notification Received
June 26, 2018 Modification Received
June 26, 2018 Application Granted
April 18, 2018 Application Granted
April 18, 2018 Change of Ownership Received
January 2, 2018 Application Granted
January 2, 2018 Construction Notification Received
October 19, 2017 Application Granted

Need Extended Tower Data?

Answer 6 questions — get early access to new features.

  • Export / API / change notifications
  • Owner (FRN), application history, Planned vs Built
  • Contact information (phone, email, attention person)
Get Early Access (2 minutes)

We don't spam. We'll only contact you about selected features.

Rendered in 1056.62ms